The following is information and news related to Takahama Unit 1 restart operations, mainly OE information released by the Kansai Electric Power Company.
| Date | Title | Information source | Remarks |
|---|---|---|---|
| August 28, 2023 | Restart to Commercial Operation of Takahama Unit No.1 | Kansai Epco | |
| August 5, 2023 | Start of Constant Rated Thermal Power Operation at Takahama Unit No.1 | Kansai Epco | |
| August 2, 2023 | Start of Power Control Operation at Takahama Unit No.1(Connection of Generator in Parallel) | Kansai Epco | |
| July 28, 2023 | (Comment) Announcement of Takahama Unit No.1 Startup | Kansai Epco | |
| July 28, 2023 | Takahama Unit No.1 Startup | Kansai Epco | |
| July 26, 2023 | Schedule of Takahama Unit No.1 Reactor Startup and Power Control Operation | Kansai Epco | |
| June 25, 2023 | Completion of Fuel Loading at Takahama Unit No.1 | Kansai Epco | |
| June 21, 2023 | Restart Process of Takahama Units No.1 and No.2 | Kansai Epco |
|