Activity Results

OE Information related to Ikata Unit 3 restart

The following is information and news related to Ikata Unit 3 restart operations, mainly OE information released by the Shikoku Electric Power Company.


Date Title Information source Remarks
Sptember 7, 2016 Ikata Unit 3 starts normal operation Shikoku Electric Power Co., Inc  
August 22, 2016 Ikata Unit 3 started constant rated thermal power operation Shikoku Electric Power Co., Inc  
August 15, 2016 Ikata Unit 3 has started generating power Shikoku Electric Power Co., Inc  
August 12, 2016 Ikata Unit 3 reactor start-up Shikoku Electric Power Co., Inc  
August 5, 2016 Ikata Unit 3 restart operation process Shikoku Electric Power Co., Inc  
August 1, 2016 Ikata Unit 3: Recovery of RCP-3B Shikoku Electric Power Co., Inc  
July 25, 2016 Ikata Unit 3: Investigation of No.3 Seal of RCP-3B Shikoku Electric Power Co., Inc  
July 17, 2016 Ikata Unit 3: The Reactor Coolant Pump (RCP) No.3 Seal Leakoff Rate Increase Shikoku Electric Power Co., Inc  
June 27, 2016 Ikata Unit 3 finished fuel loading Shikoku Electric Power Co., Inc  
June 24, 2016 Ikata Unit 3 has started fuel loading Shikoku Electric Power Co., Inc