The following is information and news related to Genkai Unit 4 restart operations, mainly OE information released by the Kyushu Epco
| Date | Title | Information source | Remarks |
|---|---|---|---|
| July 19, 2018 | Return to Commercial Operation of Genkai Nuclear Power Unit No.4 | Kyushu Epco. | |
| June 19, 2018 | Restart of Generating Electricity of Genkai Nuclear Power Unit No.4 | Kyushu Epco. | |
| June 16, 2018 | Startup of Genkai Nuclear Power Unit No.4 | Kyushu Epco. | |
| June 15, 2018 | Schedule of Startup and Restart of Generating Electricity of Genkai Nuclear Power Station Unit No.4 | Kyushu Epco. | |
| May 15, 2018 | Kyushu Electric Power informs the cause and counter measure about the increase of flow of RCP seal of the Genkai NPS Unit 4 | Kyushu Epco. | |
| May 3, 2018 | Examination around the reactor coolant pump seal is to be conducted | Kyushu Epco. | |
| April 24, 2018 | Genkai Nuclear Power Unit No.4 has finished fuel loading | Kyushu Epco. | |
| April 19, 2018 | Genkai Nuclear Power Unit No.4 begins fuel loading | Kyushu Epco. |
|