July 19, 2018 Return to Commercial Operation of Genkai Nuclear Power Unit No.4 Kyushu Epco.  
June 19, 2018 Restart of Generating Electricity of Genkai Nuclear Power Unit No.4 Kyushu Epco.  
June 16, 2018 Startup of Genkai Nuclear Power Unit No.4 Kyushu Epco.  
June 15, 2018 Schedule of Startup and Restart of Generating Electricity of Genkai Nuclear Power Station Unit No.4 Kyushu Epco.  
May 15, 2018 Kyushu Electric Power informs the cause and counter measure about the increase of flow of RCP seal of the Genkai NPS Unit 4 Kyushu Epco.  
May 3, 2018 Examination around the reactor coolant pump seal is to be conducted Kyushu Epco.  
April 24, 2018 Genkai Nuclear Power Unit No.4 has finished fuel loading Kyushu Epco.  
April 19, 2018 Genkai Nuclear Power Unit No.4 begins fuel loading Kyushu Epco.